Main Framework¶
Timetable proposed by Traversées (tender)¶
- [Last week of July 2024]: Building up of the digital infrastructure.
Setup of a new dedicated server located in Europe (Hetzner or OVH with a hardware profile close to CPU 40 cores, RAM 128Gb, NVMe SSD disks).Setup of a scalable virtualization environment (based on the open technologies Proxmox, KVM, LXC).Configuration of a working digital environment splitted into a production server and a development server, featuring tools for collaboration and code building (Redmine, GIT).Setup of a security backup and server monitoring policy (Zabbix).
- [Weeks 1 and 2 of August 2024]: Coordination and installation of the main core of Moodle, duplicating the configuration of edu.ripess.eu.
Briefings with the project’s coordination (identification of contacts, semantic updating of the project, planning).Installation of the core components and extensions of Moodle (internationalization, Big Blue Button, monitoring) using the model built for edu.ripess.eu.Installation and testing of a Big Blue Button/Fair Blue virtual server (or a cluster of servers if it is necessary to host up to 300-400 simultaneous participants).Graphic customization of the Moodle interface according to the existing visuals of the YOU CARE project and other institutional brands.
- [Week 3 of August 2024]: Tests and adaptation of Moodle and first internal learning session for administrators.
Customization of the server for a high-performance rendering, able to host more than 1000 users and up to 200 video conferencing participants (caching, optimization of SQL, PHP, Apache/Nginx, eventually load balancing and multi-servers).Installation of a Big Blue Button streaming extension, to be connected with the open video server Peertube.Installation of a self-hosted Peertube video server (with a high performance configuration).Configuration of a Moodle’s common extension for users’ monitoring and statistics.
- [Month 9-12 of 2024]: Training and enhancement of the platform to an assembly functionality
Feasibility of creating a task group of facilitators of the platform.Installation and testing of a forum/assembly functionality, based on Matrix (instant messaging integrated to Moodle 4.3), or Discourse (advanced community forum and knowledge base).Development of missing or additional functionalities; improvement of graphic templates.Trainings of the project’s coordination (and eventually the facilitators group).
- [Month 1-6 of 2025]: Reporting, training and supervision of the platform
First report based on statistics, shared contents in the platform and emerging interactions.Supervision and maintenance of the platform (core and components optimization, security checking).Activation of the participative assembly module (March 2025).Trainings and a working group of the project’s coordination (and eventually the facilitators group).
- [Month 6-12 of 2025]: Reporting, training and supervision of the platform
Second report based on statistics, shared contents and emerging interactions.Trainings of the project coordination (and eventually the facilitators group).Maintenance of the platform (core and components update, security checking).
- [2026-2027]: Reporting, training and supervision of the platform.
Updated by Francois Soulard over 1 year ago · 1 revisions