### Timetable proposed by Traversées (tender)
5
6
*  [Last week of July 2024]: Building up of the digital infrastructure.
7
> *        Setup of a new dedicated server located in Europe (Hetzner or OVH with a hardware profile close to CPU 40 cores, RAM 128Gb, NVMe SSD disks).
8
> *        Setup of a scalable virtualization environment (based on the open technologies Proxmox, KVM, LXC).
9
> *        Configuration of a working digital environment splitted into a production server and a development server, featuring tools for collaboration and code building (Redmine, GIT).
10
> *        Setup of a security backup and server monitoring policy (Zabbix).
11
12
*    [Weeks 1 and 2 of August 2024]: Coordination and installation of the main core of Moodle, duplicating the configuration of edu.ripess.eu.
13
> *        Briefings with the project’s coordination (identification of contacts, semantic updating of the project, planning).
14
> *        Installation of the core components and extensions of Moodle (internationalization, Big Blue Button, monitoring) using the model built for edu.ripess.eu.
15
> *        Installation and testing of a Big Blue Button/Fair Blue virtual server (or a cluster of servers if it is necessary to host up to 300-400 simultaneous participants).
16
> *        Graphic customization of the Moodle interface according to the existing visuals of the YOU CARE project and other institutional brands.
17
18
*    [Week 3 of August 2024]: Tests and adaptation of Moodle and first internal learning session for administrators.
19
> *        Customization of the server for a high-performance rendering, able to host more than 1000 users and up to 200 video conferencing participants (caching, optimization of SQL, PHP, Apache/Nginx, eventually load balancing and multi-servers).
20
> *        Installation of a Big Blue Button streaming extension, to be connected with the open video server Peertube.
21
> *        Installation of a self-hosted Peertube video server (with a high performance configuration).
22
> *        Configuration of a Moodle’s common extension for users’ monitoring and statistics.
23
24
*    [Month 9-12 of 2024]: Training and enhancement of the platform to an assembly functionality
25
> *        Feasibility of creating a task group of facilitators of the platform.
26
> *        Installation and testing of a forum/assembly functionality, based on Matrix (instant messaging integrated to Moodle 4.3), or Discourse (advanced community forum and knowledge base).
27
> *        Development of missing or additional functionalities; improvement of graphic templates.
28
> *        Trainings of the project’s coordination (and eventually the facilitators group).
29
30
*    [Month 1-6 of 2025]: Reporting, training and supervision of the platform
31
> *        First report based on statistics, shared contents in the platform and emerging interactions.
32
> *        Supervision and maintenance of the platform (core and components optimization, security checking).
33
> *     Activation of the participative assembly module (March 2025).
34
> *     Trainings and a working group of the project’s coordination (and eventually the facilitators group).
35
36
*    [Month 6-12 of 2025]: Reporting, training and supervision of the platform
37
> *        Second report based on statistics, shared contents and emerging interactions.
38
> *        Trainings of the project coordination (and eventually the facilitators group).
39
> *        Maintenance of the platform (core and components update, security checking).
40
41
*    [2026-2027]: Reporting, training and supervision of the platform.